Former Member
Feb 10, 2010 at 06:05 AM

post MRP run issue

23 Views

Dear friends,

After MRP run there are lot of purchase requisition generated and the purchase requisition has been converted to PO, but later on we found that for some materials belong to these orders has been purchased already by manually creating the PO earlier and they are in stock.

Now what kind of action need to be taken on these open PO. Now i have put deletion flag to the line item for which material already present and i have also put delivery completion indicator.

Now my only concern is again the same material requirement in the form of pr should not generate when i run the MRP next time, for this whether i have to close the planned order also apart from closing PR or is there any other maethod to be followed, please suggest me

Regards,

Krishna