I am abaper. i am new to PS
I have a project number with me i need to change the plan value of that project ie i need to change the table COSP field WOG002
I think i am looking for plan value change in the period 2
How can i do this ? ( I am looking for what transaction and how )
a®
Hi,
In Projects,we use various type of cost planning.
1.Manual cost planning through CJ40,CJR2.
2.Automatic cost planning through Network Costing in CJ20N
3.ECP in CJ20N.