MRP using split valuated material!

Former Member
0 Kudos

Dear friends,

I intend to run MRP using a split valuated material. What are the settings to pick the material that i want t

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

MRP will not give desired results for split valutaion. I mean to say If a material XXXX has valuation type A and B. MRP plans at XXXX not XXXXA and XXXXB. Manual intervention is always required when you convert planned order or RP to PO.

Hope my answer helps you

Regards

Antony