on 02-03-2010 2:14 PM
Hi
I have requirement that Goods Receipt should not happen before the specifed delivery date mentioned in the Purcahse Order.
Is there any customization for the same?
Regards
Hi,
In standard system, there is no connection between the PO date and
GR date. But the system can be setup in order to meet your
expectation.
You can use enhancement MEFLD004 (EXIT_SAPLEINR_004) to set the
'Earliest possible delivery date'. Here you can use the PO date to
define it. In addition you will have to customize system message M7254
as Warning or Error. Then MIGO will behave as expected.
Best Regards,
Arminda Jack
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.