Remordplan value in the report S_ALR_870130558

Hi

Can anyone explain how remordplan value is calculated, which reflects in the report S_ALR_870130558. Where we can find details of this value?

regards

Sanjay Karnekar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Feb 03, 2010 at 12:47 PM

    Hi,

    Please search the forum ,there are various threads available for this question.

    Muzamil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 03, 2010 at 01:32 PM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 03, 2010 at 01:34 PM

    Sanjay

    The remaining order plan is a key figure of a WBS element and is calculated temporarily with value type 25 during report execution as follows, for example, per order:

    apportioned planned costs of the order - actual cost of the order - commitments of the oder = xxx.

    If xxx > 0, this xxx represents the contribution of the order to the remaining order plan value of the WBS element

    - otherwise the contribution is zero.

    Hope this helps

    Rgds

    Martina