on 02-03-2010 12:46 PM
Hi
Can anyone explain how remordplan value is calculated, which reflects in the report S_ALR_870130558. Where we can find details of this value?
regards
Sanjay Karnekar
Sanjay
The remaining order plan is a key figure of a WBS element and is calculated temporarily with value type 25 during report execution as follows, for example, per order:
apportioned planned costs of the order - actual cost of the order - commitments of the oder = xxx.
If xxx > 0, this xxx represents the contribution of the order to the remaining order plan value of the WBS element
- otherwise the contribution is zero.
Hope this helps
Rgds
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please search the forum ,there are various threads available for this question.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.