Remordplan value in the report S_ALR_870130558

Former Member
0 Kudos

Hi

Can anyone explain how remordplan value is calculated, which reflects in the report S_ALR_870130558. Where we can find details of this value?

regards

Sanjay Karnekar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Sanjay

The remaining order plan is a key figure of a WBS element and is calculated temporarily with value type 25 during report execution as follows, for example, per order:

apportioned planned costs of the order - actual cost of the order - commitments of the oder = xxx.

If xxx > 0, this xxx represents the contribution of the order to the remaining order plan value of the WBS element

- otherwise the contribution is zero.

Hope this helps

Rgds

Martina