SAP PP strategy 10,11,20 and 40 difference with example.

former_member597690
Participant
0 Kudos

Dear all,

i want to understand strategy 10,11,20 and 40 with output results.

like if we have

PIR- 100

Stock- 25

Sales order- 40

Then what will be the result of these different strategy.

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Arpit
Thanks for the kind feedback.
If there are no further questions, Kindly close the thread, by accepting the solution provided. Best Regards : Raja

Accepted Solutions (1)

Accepted Solutions (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert

Hi
Please take a look of the below thread, where you can find some useful info.

https://answers.sap.com/questions/140084/planning-strategy-explanation-with-example.html?childToView...

Also, would like to suggest you to explore this standard information, from the sap help documentation & the some blogs/threads.
Hope this helps your question. Thanks & Regards : Raja
former_member597690
Participant
former_member597690
Participant
0 Kudos

hi RAJA SEKHARA REDDY BANNURU can you please give example of strategy 11 and 20 as well ?

Answers (4)

Answers (4)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert

Hi Arpit
Please find the below attached scree shot, for your scenario

Hope, this will helps you. Kindly try at your end, with some test data, you can visualize more better.
Thanks for your kind understanding. Please close this thread, if no further questions.
Best Regards : Raja

former_member202945
Participant
0 Kudos

Hi Arpit,

Can u see my latest reply and close this thread.

Thanks,

Saikrishna.

former_member202945
Participant
0 Kudos

Hi Arpit,

Raja has given example for "Make To Stock S"trategy -11". We can observed that MRP has considered only Independent Requirements though there is CustOrder = 40 EA and Stock of 25 EA, Planned Order is generated for the PIR Qty of 100 EA.

Similarly for Make To Order Strategy =20, MRP will not consider the existing Stock and Planned Independent Requiremnt,MRP Considers only the Customer Order. In the above example if the Strategy is 20 then after MRP Planned Order will be 40EA with respect to CusOrd=40EA.

Hope this clarifies your queries.

Thanks,

Saikrishna.

former_member202945
Participant
0 Kudos

Hi Arpit,

Planning Strategy 11 is a Make To Stock Strategy called as Gross Requiremnts Planning.In this strategy Sales orders does not have any impact only Planned Independent Requiremnts are considerd.

Planning Strategy 20 is Make To Order Strategy where the Planning is done based on Sales Orders.

Hope this helps.

Regards,

Saikrishna.

former_member597690
Participant
0 Kudos

Hello Saikrishna P,

thank you for respond, can you explain it with example

like if we have

PIR- 100

Stock- 25

Sales order- 40

Then what will be the result of these different strategy.