new planned orders on next project MRP

Hi All,

On project MRP for WBS, plan ordes created for different material attached to WBS. finish date of one planned order which was scheduled nearlly 12 month later from todays date on MRP run was prepone to end of this month only. on next MRP run system create duplicate planned orders for same material. what may be the reason.

Regards,

Roshan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 03, 2010 at 06:07 AM

    Hi,

    Run MRP again with Planning mode option 3(Delete and recreate planning data),hope it will help you.