Hi Experts
I have maintained default measurement method for project object types (WBS, NWA) in customizing.
But still, the method 0-100 is defaulted.
Is it essential to maintain the project version for all the project objects manually?
Is there any setting to default the project version for project objects?
warm regards
ramSiva
ramSiva,
the progress version needs to be maintaintained in EACH project object to analyze. Check F1 help for Progress version field in the WBS element.
Progress version cannot be defaulted in project profile or network profile. I doubt a substitution will help here either. I guess it should be completed manually in the standard system.
Best regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Create a Template(Std project) and default the Progress version and Measurement Method and create operative projects from this template so that Progress version and Measurement Methods will come automatically.
Also you can create your new operative projects with reference to some other operative project where you have maintained the version and the measurement methods.
Muzamil