Progess Measurement method determination error.

Hi Experts

I have maintained default measurement method for project object types (WBS, NWA) in customizing.

But still, the method 0-100 is defaulted.

Is it essential to maintain the project version for all the project objects manually?

Is there any setting to default the project version for project objects?

warm regards

ramSiva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 02, 2010 at 11:24 AM

    ramSiva,

    the progress version needs to be maintaintained in EACH project object to analyze. Check F1 help for Progress version field in the WBS element.

    Progress version cannot be defaulted in project profile or network profile. I doubt a substitution will help here either. I guess it should be completed manually in the standard system.

    Best regards

    Martina

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Create a Template(Std project) and default the Progress version and Measurement Method and create operative projects from this template so that Progress version and Measurement Methods will come automatically.

      Also you can create your new operative projects with reference to some other operative project where you have maintained the version and the measurement methods.

      Muzamil