on 11-30-2018 3:17 PM
Creating work order and setting start date to 12/10 with forward scheduling
When I schedule the work order start date jumps to 12/20
Not sure why since no holiday or factory calendar blocking see calendar below:
something else odd when going to routing/schedule see interoperation times of 4 days which would indicate a float
but when checking CEWB no interoperation times
Any guidance on the 2 questions:
1. Why can I not set start date for work order to 12/10?
2. Where are the days of interoperation time coming from?
we do not have PP/DS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
This question was opened in the Embedded PP/DS tag, so the question is: are your operations integrated with PP/DS? I'm asking because your screenshots are only showing information from the ERP PP side.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.