Hi guys,

in a CS notification you can include several tasks to be completed. When you complete a task and don't specify the completion date, the system takes current system date.

However my customer sais that it should be possible to put a completion date for a task into the future (for planning reasons).

IS this correct? ..because I don't find any customizing settings for modifying this (keep having the error :'date is in the future')

regards,

bert

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Feb 01, 2010 at 09:11 AM

    Hi,

    First releas the task and then try to put future date

    Kapil

    Edited by: Kapildev Farakte on Feb 1, 2010 2:42 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.