Dear Experts,
Please note that I am attaching two finished goods (Material Type - FERT) in the project through network activity, on two different activity. The delivery time for the two items are different. Requirement date is one month different for the two finished goods.
Requirement Grouping is done through automatic grouping.
Now when I am running MRP system generates seperate planned order for two finished goods for the same raw material as the requirement date is different. If I am keeping the requirement date is same even though it is planned on different network activity system is making only one planned order for the total number of raw material required.
Just one doubt..
Is there any work around to club the requirements of raw material for two finished goods, whose requirement date is different, in one planned order / purchase requisition.
Thanking you.
Best Regards,
Abdul.