Dear all,

We are using STO scenerio with strategy 20, requirement comes in depots ,depots will be created sale order and then run the MRP in depots system will create PR against sale order in depots and pass the requirement to manufacturing plant and sytem will create planned order against SO in manufacturing plant

when i am traying to covert plannned order to process order system has given me below error "Technical status 000000000000 is not available

Message no. CC852

Diagnosis

An internal error has occurred. There is a data inconsistency. The system cannot find the parameter variant data.

System Response

The system does not allow processing to continue.

Procedure

Inform your system administrator. If the error cannot be corrected, contact the SAP Hotline directly.

For MTS (strategy 40 ) - above scenarion working fine