on 01-28-2010 5:46 PM
Hello to everyone,
I have created a release strategy for the purchase order and I have selected Changeability = 6. In this way when someone change the amount after the purchase order has been released, a new strategy is generated. But this happend only when you increase the amount. Is there any way to generate a new release strategy when you decrease the amount?
Kind Regards
Hello,
You may use CEKKO-REVNO and set version as characteristic of release class. Then any changes to PO will trigger release procedure, no matter value increase or decrease.
Hope this helps.
JM