Hello SAP Gurus,
In LTP scinario Sir I have run the MS02 for FERT material but in my case I have FERT-HALB-ROH means multileval BOM but after MRP run system planed for only FERT no any praposal created for the HALB and for ROH material what may be reasion of this?
regards
Hello,
Have you maintained BOM selection ID in Planning Scenario (MS31)
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. IN the MS32 Kindly check what is your BOM selection ID- here you need to keep the proper id for selecting the BOM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.