LTP

Former Member
0 Kudos

Hello SAP Gurus,

In LTP scinario Sir I have run the MS02 for FERT material but in my case I have FERT-HALB-ROH means multileval BOM but after MRP run system planed for only FERT no any praposal created for the HALB and for ROH material what may be reasion of this?

regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

Have you maintained BOM selection ID in Planning Scenario (MS31)

Regards

Former Member
0 Kudos

Hello Sir,

In MS32 i have maintened BOM selection ID 02 am wrong here?

regards

Answers (1)

Answers (1)

Dsk
Active Contributor
0 Kudos

Hi,

1. IN the MS32 Kindly check what is your BOM selection ID- here you need to keep the proper id for selecting the BOM.