Hi Experts,

Can anyone tell me how to updated public holidays in Golden client. B'coz when I am logging into the Golden Client it is not giving me the option of changing public holidays.

Thanks & Regards

Lalit

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2010 at 07:16 AM

    Hi Lalit,

    You need to update the public holidays in SCAL transaction in development client and use the "transport" button to carry them into other clients.

    If the "Golden client" is supposed to be a "development client" then please make your basis team make system "changes allowed" status via transaction SCC4.

    Regards,

    Dilek

    Edited by: Dilek Ersoz Adak on Jan 28, 2010 8:17 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2010 at 07:18 AM

    Once I too faced the same issue, with the help of Basis people we can get it done.

    Co-ordinate with ur Basis team.

    Kind Regards,

    Saisree.s

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.