During picking TO creation the system automatically determines the source storage bin from where the materials should be picked. Lets say the items to be picked are not there and cannot be picked. In this case the operator should be enabled to pick from another storage bin, however the system does not allow this. (This is via mobile data entry and in a bulk SU manages st. type).

Is there a way to allow picking from another storage bin? If not, can the TO be created without any source determination? Even if I switch off picking strategy, the system expects entry of source bin at TO creation.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

With out a source storage bin , pick TO cannot be created currently. If at all you want a different source bin, you have to cancel the TO, block the current bin and then recreate the TO. That is an exceptional case and should be handled inside the system.

Thanks

Vinod.