on 11-24-2016 11:09 PM
Hello Experts,
I want to avoid a BOM component from planning and that component is relevant to costing, so dont want to use bulk material. Please explain.
Thanks,
Suresh.
Hello Caetano,
I am trying to set the Bulk material indicator, however it is not allowing as it is relevant to costing.
What is the effect of removing costing relevancy to the component.
Regards,
Suresh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
If you need a more specific logic to exclude the component from the MRP planning, you can also use BAdI MD_CHANGE_MRP_DATA.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.