How to avoid a BOM component from planning

Hello Experts,

I want to avoid a BOM component from planning and that component is relevant to costing, so dont want to use bulk material. Please explain.

Thanks,

Suresh.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 28, 2016 at 04:21 PM

    Hello

    If you need a more specific logic to exclude the component from the MRP planning, you can also use BAdI MD_CHANGE_MRP_DATA.


    Regards,
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 28, 2016 at 11:18 PM

    Hello Caetano,

    I am trying to set the Bulk material indicator, however it is not allowing as it is relevant to costing.

    What is the effect of removing costing relevancy to the component.

    Regards,

    Suresh.

    Add comment