is it possible to post PO and GL Posting to WBS with out Budget

Hi

is it possible to post PO and GL Posting to WBS with out Budget.

reason for both the case ( if possible or if not possible).

Regards,

Vamsi.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 27, 2010 at 07:12 AM

    It is possible.

    To generate PO and post a GR, you require an account assignment.

    To make a GL posting, you require a CO object.

    The WBS element can be used in both the case irrespective of whether it has budget or not as it is a CO object and can be used as account assignment.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      Thanks a lot

      But is it require Budget allocation to WBS for execute the RA (Result analysis for Projcet)

      Can You give sugesstion

      regards

      vamsi

  • avatar image
    Former Member
    Jan 27, 2010 at 07:30 AM

    Hi,

    Please check the other threads releated to this question.

    Please understand why we are using Budgeting Functionality in projects...

    You can post without budgeting but there will no control on cost overrun.