on 01-27-2010 6:39 AM
Hello All,
How can we capture the Planned and Actual costs of all the activity elements (Activity Internal / Material Components) in an activity?
I have an activity by name: Concreting Work, in this acitivity i have activity elements as mentioned below
Concreting Work -
> Activity
Labour 50 H -
> Activity Element
Self Loder 5 H -
> Activity Element
Vibrator 2 H -
> Activity Element
Water Tanker 4 H -
> Activity Element
Two Wheller 2 L -
> Activity Element
Four Wheller 1 L -
> Activity Element
01-SAND 2 M3 -
> Materail Component
01-CEMENT 80 BAG-------> Materail Component
01-MAT-12 5 M3 -
> Materail Component
01-MAT-20 4 M3 -
> Materail Component
01-MAT-40 1 M3 -
> Materail Component
Now my query is that is there a way in which i can see all the Plan/Actual costs of the activity elements, (Activity Internal / Material Components) of the activity Concreting Work.
Regards,
Sudarshan.
Hi,
Use CN41/CN41N and other PS reports under PS01.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Thanks for your replies,
i was trying to execute the report "S_ALR_87013532 - Costs -> Plan-Based -> Hierarchical -> Plan/Actual/Variance ", here i am able to track the Plan/Actual costs of the activity.
But in this report , i can only see the activity elements but not the material components of the activity.
The Plan value of concreting is Rs.10000/-, which includes the activity element cost of Rs. 2500/- and the material component cost of Rs. 7500/-.
But when I execute the report, the display is as follows, here I am unable to see the material components but the cost is included in the output.
Concreting (10000)
-
>activity elements (2500)
Can any one tell me why the cost of material components are not displayed in this report "S_ALR_87013532 - Costs -> Plan-Based -> Hierarchical -> Plan/Actual/Variance ",
Regards,
Sudarshan
in S_ALR_87013532 all costs will appear against the activity - this is because you are using activity account assignment in your network profile - meaning the cost collector is the network activity - as far as the system is concerned the labour, material etc are all types of cost collected by the activity
Go to report S_ALR_87013532 and check your DB profile Material Componentt might not selected there. That why report is not showing you. Select material Component in DB profile ( use DB profile 000000000001 ) and execute the report. Apart from that As Virendra told PS cost component is Network activity based on configuration, show all the cost will get diaplyed against netwrok activity.
With Regards
Nitin P.
Hello Virendra,
Thanks for your reply.
I didnot get you in your earlier reply.
Can you please elobarate the same, as to why the material components are not displayed in this report "S_ALR_87013532 - Costs -> Plan-Based -> Hierarchical -> Plan/Actual/Variance".
Here the Activity cost calculation gives me the addition of activity elements and material components, but display is only for activity elements.
Regards,
Sudarshan
yes all the plan and actual costs will be visible in PS reports
Transaction PS01 - go to Financials
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.