Skip to Content
avatar image
Former Member

PS report remainder no detail

in report S_ALR_87013558, under one investment program and WBS element, we can see details of budget/actual/commitment,

but under RemOrdPlan column, it shows total of 233390 USD, we drill down to the network level, but every network/activity level for RemOrdPlan is zero, how can I know the details of 233390? which table can i use to find valuation type 25, which defined Remordplan?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 27, 2010 at 06:12 AM

    Hi,

    remove the plan cost variant from assigned network header-control tab......and save.....

    remaining order plan will be removed...

    Regards

    Ashis

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      No.

      I want to keep it.

      there is a lot of discussion on this forum and most are releated to the calculation of RemordPlan.

      My question is different, I don't care about calculation, I want SAP shows the break down (detail figure for each network/activity)for this RemOrdPlan.

  • avatar image
    Former Member
    Feb 03, 2010 at 02:21 AM

    thanks

    Add comment