on 01-26-2010 7:42 PM
Dear Consultants,
i'm using many inactive versions for DM and one active version which is 00
the problem is: to make sure that the active version is clear from old PIRs before copy the new demand to the active version
i have to initilize (clear) the version.
how to clear the active DM version ?
-
and the same i'm using many inactive versions for SOP (planning versions)
and the same problem is how to clear the SOP planning version?
thank you,
any suggestions ...