How do you release Mass Maitnenance Plans set on Hold

Hello,

After upgrade it seems that our Plant Maintenence:maintenance plans status are set to "Schedule Hold" and has not released any calls.

Is there a way to release the maintenance plans for all,so the schedule will continue as usual.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 27, 2010 at 04:05 AM

    Hi,

    Go to IP15

    Execute

    Select all plans

    Miantenance plan >>> schedule

    Click on save, then schedule next plan, save

    Kapil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.