01-25-2010 3:09 PM
Can you let me know any BAPI / Function Module to update work centre for given planned order. BAPI planned order change doesn't suit this requirement.
01-25-2010 3:55 PM
01-25-2010 5:02 PM
Hi,
I checked BAPI_ALM_ORDER_MAINTAIN, but that couldn't change the work center and there is no parameter to pass planned order. Let me know if any that suits th erequirement. I have planned order number, plant, material, work center details, i need to change the work center with planned order number as key.
01-31-2010 11:22 PM