Hi all,

We have an SRM 7.0 system and EHP 4.0 as our backend system and we wish to enable the service procurement scenario (document exchange between EHP 4.0 & SUS).

I will be using the standard scenario provided by XI/PI to enable this scenario.

But in XI/PI there is a standard scenario provided by SAP by the name "Service Procurement with Supplier Enablement" in which the 2 systems between which document exchange is possible are SRM & SUS instead of EHP 4.0 & SUS(as required by us).

Let me know how to proceed.

Thanks

Nikhil

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 25, 2010 at 12:56 PM

    Pls chek the note 1268336 and 1263876

    Regards

    Kiran

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 26, 2010 at 06:32 AM

    Hi Nikhil,

    For service procurement you can use the following :

    SE_Services_Procurement for (MM - SUS)

    SE_Sourcing_Enhancements (MM- EBP- MM)

    If you use both then the complete business scenario can be completed (MM-EBP-MM-SUS-MM)

    Regards

    Sam

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Nikhil,

      We have a similar requirement as yours.

      We are on SRM 7.0 and ECC6 EHP4. The CPPR scenario is active and is working fine for materials and services.

      But for MM-SUS we are still using the Idoc method (scenario plan_driven_procurement_SupplierEnablement). So the PO output from SAP is idoc instead of XML.

      We want to switch to XML mode to exploit MM SRV-SUS scenario (service procurement classic).

      I understand that we now need to configure scenario SE_Services_Procurement in XI instead of plan_driven_procurement_SupplierEnablement. But apart from XI configuration is there any ECC step to be done? We have already activated LOG_MM_P2PSE_1 in ECC. Is there any other change required (over and above existing MM-SUS PDP scenario settings) in ECC?

      Regards,