Hi Alll,

Can i make apilling plan at my contract but at time of bill issue make this bill delivery related instead of order related.

if i can pleases tell me the setting in configuration to do it.

thanks alot.

Accepted Solutions (1)

Accepted Solutions (1)

ivano_raimondi
Active Contributor
0 Kudos

Hello,

it is not possible.

Best regards,

Ivano.

Answers (2)

Answers (2)

jpfriends079
Active Contributor
0 Kudos

> For your information: Milestone billing is typically used for billing projects, such as plant engineering and construction projects. Such projects often include a series of milestones that mark the completion of different stages of the work. In the SAP R/3 System, milestones are defined in a network along with planned and actual dates for the completion of work. The milestones are also assigned to the billing dates in the billing plan. Each milestone-related billing date is blocked for processing until the Project System confirms that the milestone is completed.

Delivery-relevant order items for which a milestone billing plan applies are billed on the basis of the requested delivery quantity and not on the total of the confirmed quantities.

Hope it assist in your cause.

Thanks & Regards

JP

0 Kudos

Hi ,

Check you copy controls-maintaintenace for Billing doc- Maintain with refeence to order