cancel
Showing results for 
Search instead for 
Did you mean: 

PS Integration with PP with respect to Make to order projects

Former Member
0 Kudos

Hi Experts,

I have a requirement that our customer is having only Make to order projects ,In this aspect Is there any Integration with PP.

Thanks In Advance.

Regards

Madan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In MTO,You have to deliver the goods as per the customer requirements so if you are producing it in your plant then PP is important otherwise if you purchase it from third part then no need of PP.

Muzamil

Former Member
0 Kudos

Hi ,

Thank you very much .

Here we are producing in the same plant .

Can I have the scenario how it works...

Thanks in Advance

regards,

Madan.

Former Member
0 Kudos

Hi,

Please search the forum there are various threads releated to this topic.

There are various ways doing this.

Attach a finished material to the activity in cj20n and then run MRP .System will create Planned Orders/PRs on the basis of Material type whether the material is meant for internal Production or for prourment.

So in your case after MRP,a planned order will be created and then you convert to a Production Order.

Issue the raw materials to the production order and confirm the operations and a finished product will be produced and then you issue to your project.

Muzamil

Former Member
0 Kudos

Solved

virendra_pal
Active Contributor
0 Kudos

if for the make to order you actually produce certain parts then there will be integration with PP