Case:
Non-valuated project stock
Component should be delivered from plant stock to customer
Process that is working as expected:
1. Component assigned to NW Activity by "Reservation for Network"
2. Create delivery with CNS0
3. Post Delivery picking and GI
-> Cost posted to NW activity and component issued from plant stock
But what should be process if cost should be posted to project long time before delivery will happen?
I have tried following:
1. Component assigned to NW Activity by "Reservation for Network"
2. MB1A movement 281 To reservation
-> Cost posted to NW activity and component issued from plant stock
Even delivery can be created with CNS0 if you mark checkbox "Open quantity 0"? And reservation is already fullfilled so if you pick some quantity to delivery you will get extra cost to your project.
I have tried to confirm NW Activy. It did'nt help.
I have also tried to use negative quantity:
1. Component assigned to NW Activity by "Reservation for Network" two times: Positive and negative quantity
-> Component with positive quantity: Movement parameter = 281
-> Component with negative quantity: Movement parameter = 581
2. MB1A movement 281 To reservation
-> Cost posted to NW activity and component issued from plant stock
3. Confirm activity
But: I can't get component with negative quantity to CNS0 delivery. I can't GR 581 that by-product back to plant stock.
What is correct process to GI component to Network, process that there and deliver it to customer?