on 01-20-2010 4:03 PM
Hi,
There are CIT documents(probably called configuration input templates ) prepared in SAP. These documents involve the high level description of the scenario and then they consist of the configuration steps (menu path etc) and the data required to do configuration (for eg the various sales doc type etc). these CIT helps a configurer to do config in the system.
my question is, are these CIT's, prepared at the end stage of blueprint or at the start of the realization phase ??
regds
Hi,
CIT will be prepared in the Realisation Phase, Using these CIT documents IT Team will take sign off to start the Configuration in SAP from Business.
regards,
santosh