I want config and settings to be maintained in material master for availability check

Regards

Dushyant Sharma

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In material master >>> Sales ; Genral/plant data tab or in MRP 3 tab >>> you can set availablity check rules

01 - Collective (Sumarized)requirement

02-Indivisual requirement

IMG >>> SD >> Basic functions >>> Availability check & TOR >>> Availabliity check

Kapil

Edited by: Kapildev Farakte on Jan 20, 2010 2:45 PM

Former Member
0 Kudos

Do i hav to maintain mrp type also?

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Just to add on...

Availability check is carried out in different transactions like Sales order creation, delivery creation, Purchase order creation, goods issue and also in production order. The point to be noted here is everywhere the availability check is carried out using two basic elements.

1. Checking rule

2. Checking group

Explanation

Checking Rule

Checking rule is transaction based, i.e. In STD SAP system, if you are creating the sales order, then it is A, if delivery then it is B, if you are creating/releasing production order, then it is PP. This is almost fixed. What is the use of this as a single element it does not have any meaning, but with checking group.

Checking group

Checking group is the one what you assign in material master at plant level, i.e. for different plant and for the same material or for same plant different material there can be a different checking group. This is assigned in material master in MRP3 view, as a signal element it may not have much meaning except that it may be used for checking at which level - group level or individual level and quantities confirmed in the availability check are to be locked or not.

Combination of Checking rule and checking group will define the scope of check

In scope of check you will be defining all control parameters in t-code OVZ9

Checking group you have defined in MMR as 01 and system is checking with checking rule A as it is a sales order you have created

Hence the system takes the said combination

Checking rules are predefined in SAP.

Checking Rule A for Sale Order and B for Delivery is pre defined in SAP and based on the availability check what you maintain in material master, checking rule will react in sale order.

'A' refers to Sales Order and Availability check Rule determined in '01'.

Regards

Former Member
0 Kudos

Maintain the feild Availability check at page Sales: General/Plant Data page. Either Individual requirement or summrised.