Hello Experts,

I have an scenario where have created the project with reference to the sales order in the standard template along with the materials, where the same is been created in as operative project along with the standard network assigned to the material.

The problem is whenever am using the same material in the new sales order which is assigned in the earlier sales order to create the network, it always asks for the network in as soon as i enter the material in sales order, also at the mean time i am not able to delete the network created it throws the error "this is created with reference to the sales order and cannot be deleted"

Is there any way to over come this two problem, i wanna use the same material in other sales order without entering the network for that and have to delete the network created by sales order i.e.by assembly processing

Thanks