on 01-18-2010 9:15 AM
Dear guruji
we are using PPPI industries when we conform process order using t-code COR6N we got to goods movement tab with tick on clear oepn reservation.we also change Qty of material in this tab and conform process order. in MB25 there is also give diff. qty . we want to clear all reservation in MB25
Thanks
Pankaj
You could csutomize Confirmations so the open reservations are cleared with the final confirmation, Transaction OPK4 for the combination Plant / Order Type
To solve the existing open reservations, close technically the process orders and check MB25
Regards