our network activity status is rel, setc, and NCST(no actuals)

I create a PO against such network, it says

po item 0001 still contains faulty account assignments, user status NCST is active (NWA 6000723 0010)

how to correct it, thanks.

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

Hi This is due to User status NCST ( No actaul ) , check out with you PS Consultant or Ooen that projecti Cj20n and click on that activity Edit > Stats>set ( Chagne user status. )

For you NCST status I think Actaul cost posting is prohibeited that's why system is givne you that error. Get the user status prfile from Newwork activy and Chek the same in OK02 t Code for status NCST.

With Regards

Nitin P.