Skip to Content
0
Former Member
Jan 13, 2010 at 06:55 PM

Network - Activity Code filed in service purchase requisition

23 Views

Dear experts

I have a problema when using service master records in purchase requisitions allocated to a network and activity. (network of a project, we have the PS module also implemented).

It is a little bit difficult to explain it but i'll try to do my best:

When indicating the service then a new window opens to indicate the network and activity. But when a enter them and press accept (the green button), then in the line of the service it is not possible to see the activity code (four digits code VORNR). I only see the network code, so I cannot change the activity if I have put it incorrectly.

I tried to go to customizing in Materials Management - External Services Management - Define Screen Layout. And there I only found the possibility to add the network but not the activity.

Someone could help me? or know if it is possible via customizing?

Thank you in advance.