Former Member

Table value for Planned Cost - Cj30

In verge of developing an report , I need the Table value from Which I could pick 'planned cost" available in CJ30 against the project number .

Could anyone throw some lights on that ??

Regards

Muralidharan.S

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 13, 2010 at 09:48 AM

    Hi,

    As stated in the previous posts get the OBJNR from PRPS table and pass it on to the RPSCO table. YHou will get the planned value.Please make sure you excute for Value type 1.Value type 4 is for actual cost.

    Regards,

    Gokul

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 13, 2010 at 08:35 AM

    try Table RPSCO you will need to get the object number from respective table

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 13, 2010 at 08:44 AM

    Hi,

    You mean to say in CJ40 not in CJ30.

    Step 1: Go to PRPS Table and enter the WBSE and get the OBJNR no.

    Step 2:Pass the OBJNR in RPSCO and you can get the planned cost value.Note WRTTP should be 1.

    Muzamil