WBS/Activity Basic Date change

Dear All,

Our requirement is that in a project, the user should not be able to change the basic dates of any WBS/Activity after the project has been released.

Pl advise.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 12, 2010 at 07:54 AM

    In network scheduling parameters in "Adjust Dates", choose do not adjsut basic dates,reqmts to operation dates

    In WBS scheduling parameters do not check the check box for "adjust basic dates".

    Hope this will solve your problem.

    Regards,

    Mahendra

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Virendra Pal

      Thanks.

      I guess this will work for WBS, will try.

      But will the same BADI work for the Activities or do we need to do something more for the controlling dates for activities.

      Rgds,