on 01-12-2010 6:47 AM
Dear All,
Our requirement is that in a project, the user should not be able to change the basic dates of any WBS/Activity after the project has been released.
Pl advise.
Thanks
In network scheduling parameters in "Adjust Dates", choose do not adjsut basic dates,reqmts to operation dates
In WBS scheduling parameters do not check the check box for "adjust basic dates".
Hope this will solve your problem.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The scheduling parameter configuration is an interesting option - however I have a feeling that it only applies to scheduled dates and not manually adjustment by users. Check it out though
Another option would be to set the date field as display only once the WBS is released - this can be achieved using BADI WORKBREAKDOWN_UPDATE. However this would mean taht you have to double check your scheduling configuration when the system tries to write the scheduling dates to the date field and throws error messages, then you might have to remove the adjust basic dates indicator as mentioned by Mahendra.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.