CJ32 Budget exceeded

Dear All,

I have coming across a strenge error of budget exceeded while releasing budget. Two of my projects giving these error while rest is fine. Here error value is very high say in crores and not matching to any total up, addition and deletion. It gives for top level WBS element and rest two lower wbs elements.

For remedial action I have checked almost all. Also I have done CJBW abd CJBV for the same WBS elemets. We have only overall budgets. I have also checked CJI8 but no clues. We have version updates from 4.7 to 6 but rest of the projects runs well only these two gives error. Whether any note work here? please suggest.

Your solution will be higly appreciated

Rahul.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 12, 2010 at 05:02 AM

    Hi,

    It gives me error of BP603 with a abrupt value. Form which table it takes that value?

    Regards,

    Rahul.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Mohamed Rafi

      Hi Ahmed,

      We also face the same problem in our projects. In reports budget is available but while doing posting system was giving budget exceed for XXX amount.

      And SAP suggested same progrme RKANBU01 to run for the project or PO by exlpanation of inconsistency in CO tables.

      But main question is 1st why system allowed to create more commitments and not update in CO table and SAP report was giving wrong budget available data.

      After running this programe RKANBU01 values get transfered in CO table in reports also updated.

      If you have any clue please update.

      regards,