CJCF Carry Forward Commitment

Hi All,

Just have 4 relativley easy questions related to CJCF (Carry Forward Commitment) 😊

1)My project has a PO commitment of 60 USD in year 2009.If I carry forward the commitment using CJCF, will the system just change the delivery date in the PO to the first period of 2010 ?

2)Will the assigned budget value of 60 USD of 2009 move to 2010 with 60USD ?

3)Where can I see the list of carried forward Purchase Orders and its value ?

4) I believe CJCF does not carry forward PR Commitments.Is that a right assumption ?

Hope to hear from you very soon.Thanks for your help.

Jungleem

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 09, 2010 at 03:11 PM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 10, 2010 at 10:34 PM

    Hi,

    1)My project has a PO commitment of 60 USD in year 2009.If I carry forward the commitment using CJCF, will the system just change the delivery date in the PO to the first period of 2010 ?

    A: No, the delivery dates would remain as it is.

    2)Will the assigned budget value of 60 USD of 2009 move to 2010 with 60USD ?

    A: That is correct,

    3)Where can I see the list of carried forward Purchase Orders and its value ?

    A: S_ALR_87013533 transaction

    4) I believe CJCF does not carry forward PR Commitments.Is that a right assumption ?

    A: That is correct.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Contrary to your observations, i can see in both commitments in CJI5 and S_ALR report. PR commitments should also be transferred. That is correct.