Hi All,

I have created a Scheduling agreement for a material which is having an availability check of 01(Daily requirement), because of that my order number is not reflecting in MDO4. Now i have changed the availability check for that material to 02(individual requirement). Could you please suggest me how to get the order number in MD04 now? Finally we have to update availability check group as 02 in scheduling agreement also.

Do we have any program or SAP note which will help us to resolve this issue?

Warm Regards

Lakshmikanth

Accepted Solutions (0)

Answers (3)

Answers (3)

lakshmikanthc2
Active Participant
0 Kudos

Thnaks

reazuddin_md
Active Contributor
0 Kudos

Once Scheduling agreement is created for the material which has Availability check:01, as you said Order number will not be appeared in MD04, is fine upto then.

after that , if you change AC from 01 to 02. from hereon wards, these effects will get active. but will not have any impact for the old documents.

Either you can create new order OR add one more line item in the same order , but make sure to delete the old line item from that order.

Lakshmipathi
Active Contributor
0 Kudos

Not sure, just refresh MD04

thanks

G. Lakshmipathi

lakshmikanthc2
Active Participant
0 Kudos

No, No change in MD04 after refresh also,

former_member550050
Active Contributor
0 Kudos

Hi

Any corrections made in masters after a document is created will not update the already created documents (99 %in SAP)

It will apply for new documents only

You have made the changes in material master only changing availability check from 01 to 02

You need to create a fresh order and see

Regards

Raja

Shiva_Ram
Active Contributor
0 Kudos

Hi,

Try running the program SDRQCR21 in SE38 and check the results.

If not sucessful, then as mentioned before try the suggestions.