Hi,

I would like to create the Schedule for package link

Go to data manager / view status / view Schedule Status click right , I can modify or delete the Schedule but not create

How to create a schedule

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 24, 2016 at 10:45 AM

    You have to RUN a package link, then you will be asked to schedule!

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 24, 2016 at 10:53 AM

    Hi Bastien,

    Vadim is correct.

    Please refer the attached screen shot.

    Thanks,

    Karan