Skip to Content
avatar image
Former Member

Budget mandatory for any project

Hi experts

How to make that Budget is mandatory for any project?

It means, the business transaction on any project can only be allowed after budgeting.

With out opting user status, is there are way to acheive this by standard means?

warm regards

ramSiva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 09, 2010 at 08:40 AM

    Hi

    You can look at activating the availabiity control without allocating any budgets. Please check SAP note 602588 for more information.

    Once AVAC is active you may not to be able release any PRs and POs.

    Regards

    Srikrishna

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 08, 2010 at 06:16 AM

    Hi,

    I agree with Ahmed. This is not possible in the standard system.

    Regards,

    Gokul

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 08, 2010 at 06:21 AM

    Without user status, you can't do it.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 08, 2010 at 06:07 AM

    I dont think it is possible to achieve in Std. SAP without user status.

    Add comment
    10|10000 characters needed characters exceeded

    • unfortunately, there is no business transaction available for Budget Release in User status config, which can set the user status automatically. It has to be done manually. But you can restrict/allow a user to set the status by authorization key.