APO_SAPAPO/RES01

Hi,

I have defined Production shutdown using /SAPAPO/RES01.

We have defined Production shutdown for 3/3/2010 - 9/3/2010. Still we are getting 3/3/2010 as a working day in planning book, Production is planned on 3/3/2010.

I am able to see Production shutdown on downtime tab of /SAPAPO/RES01, but when I click on capacity profile single day 3/3/2010 acts as a working day.

Please help to get 3/3/2010 as a Production shutdown.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jan 08, 2010 at 05:19 AM

    Hi Rishi ,

    I hope you have defined the downtime correctly as starting from 00:00:00 hrs on 03/03/2010 and saved the resource properly.

    and you have defined this shutdown in 'Downtime'Tab of resource master.

    Else you can define shutdown period in Capacity Profile of Resource by setting these days as "Not a workday" and assign that Variant to the resource so that no orders are planned and displayed in Planning book .

    Hope this works for you ..

    Regds,Digs

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2010 at 01:13 PM

    Hi Rushikesh,

    Please check the resource planning table for your resource. If you see the capacity available on a day when you have planned downtime, then your downtime is present only in database.

    Add the downtime in live cache as follows:

    go to RES01. enter resource name, location and version; but dont go inside resource. Instead, click Tool at top and select Live cache check. input your resource and then execute. Then select your resource row and save results in Live cache.

    Please let me know in case the problem still persists.

    Regards,

    Bipin

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2010 at 07:00 PM

    Hi,

    Is your problem sloved ?

    Please let me know, whether the planned orders are considering the down time. I came across the similar problem.

    Regards,

    Ravi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.