on 01-07-2010 12:51 PM
Dear Sir,
We have defined various Activities under a WBS Element . Instead of Updating the Status of the Activity from the CJ20n screen , We want to confirm the Activities using a Z program ( utilizing BAPI etc ... ) .
Kindly guide us about the steps need to be followed for the same pl .
With Thanks and Rgds
S Agarwal
you can use BAP to confirm, write LSMW via transaction CN25 or write a Z program via CN25 or CN22 to update status etc