How to update Activity Status in PS

Dear Sir,

We have defined various Activities under a WBS Element . Instead of Updating the Status of the Activity from the CJ20n screen , We want to confirm the Activities using a Z program ( utilizing BAPI etc ... ) .

Kindly guide us about the steps need to be followed for the same pl .

With Thanks and Rgds

S Agarwal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 07, 2010 at 12:54 PM

    you can use BAP to confirm, write LSMW via transaction CN25 or write a Z program via CN25 or CN22 to update status etc