Budget availability check from assignment of budget profile in PD

Hi Experts

I have built a Project structure with assignment of a budget profile which is configured for availability check.

Before allocation of buget, i am still able to create procurement proposals manually with assignement of this project WBS elements.

The budget availability check is active only at the time of allocaiton of original budget.

I wish to bring the control as soon as the budget profile (which is subject to availability control) is assigned to project definition.

But this is not available and i am able to create manual commitments.

Is there any means of achieving my requirement?

warm regards

ramSiva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 07, 2010 at 11:47 AM

    use user status for this

    Add comment
    10|10000 characters needed characters exceeded

    • create a user status to disallow commitments (business transactions like Material Purchase req or Material Purchase Order etc), set this on CRTD system status and remove for BUDG (Budgeting)