How to transfer budget from one WBS to WBS

Dear All,

Please guide me how to transfer budget from one wbs to second wbs.

Also tell me how can i see used budget against any project

Regards,

Mahesh Wagh

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 07, 2010 at 07:11 AM

    Hi,

    The standard method is to use T Code CJ34 to transfer the budget from one WBS element to the other.

    Regards,

    Vinodh.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 07, 2010 at 06:39 AM

    You can transfer budget in transaction CJ30. Just remove amount from the WBS to the WBS where you want to allocate.

    In the report S_ALR_87013558, you can see the available figure as figure available still from budget.