on 11-18-2018 5:11 AM
i configured Dynamic Availability check for Reservation, Goods Issue and Goods Receipt.
It is working fine for Reservations and Goods Issue. I face a problem in the give scenario:
Reservation is created when stock is not available hence reservation quantity is not confirmed while checking CO09 as expected. My issue is that when Goods Receipt is done against Purchase Order and stock is made available, the same is not confirmed for the open reservations. Reservations requirement date is in the planning horizon. As a result, when a reservation is created by another user for the entire stock, the new reservation quantity is getting confirmed. We are not able to issue material for the first reservation due to error message configured.
Please give a solution to ensure that availability check takes place at Goods Receipt and quantity for the first reservations is confirmed when stock is available after GR.
I have assigned checking rule 03 to MIGO in OMCM.
Thanks in advance
I don't think it's possible to trigger automatic ATP check in a reservation when GR is posted. You'd have to recheck ATP in a reservation manually or program a custom ABAP solution here.
Dominik Tylczyński
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.