Settlement overview while creating activity

Hi Experts

When ever i create an activity for a WBS element, the system takes to the screen 'Maintain settlement rule: Overview' and gives a message 'Maintain settlement rule / distribution rule'

The overview already contains the distribution rule : WBS - Receiver WBS element, 100%, settlement type FUL and No.1

I have maintained the standard strategy 01 for the Network type+plant parameters.

What would be the reason for populating the settlement rule overview?

warm regards

ramSiva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 06, 2010 at 12:57 PM

    can't replicate

    I am never getting settlement overview on adding activity

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Virendra,

      Thanks for your exploration.

      I have further studied and observed that because of not having the settlement srtrategy for WBS elements, the settlement overview appeared.

      Temporarily i removed settlement strategy for activities too.

      warm regards