Plan driven procuremnt

Hi,

"Plan Driven Procurement" transfers Purchase requisitions created in the backend system(ERP) to SRM and subsequent processing takes place.

Does the plan driven scenario also transfer Pur Req for services to the SRM system?

The table V_T160EX allows to make settings only for material groups to be transferred to the SRM system.

Regards,

Vignesh

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 06, 2010 at 12:37 PM

    Hi

    please check thi slink

    pdp-services-pr-not-transferred-to-srm

    Regards

    G.Ganesh Kumar

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 06, 2010 at 11:58 AM

    Hi Vignesh,

    In Plan drive procurement - for direct material external requirements can be transferrred from ECC 6.0

    thro' P.R (or) Thro' MRP .For this only profile is created in the table : V_T160EX for Material Group.

    Purchase requistion for service is not taken .

    You can do one thing if you are regularly using the same services -better allot one material number and then you can transfer the requirment.

    Regards

    G.Ganesh Kumar

    Add comment