Dear Sappers,

My client has this requirement.

Purchase Order is made respect to PR.PO is released and order is placed to Vendor with quantity 100 and has a delivery date.

After placing the Order to Vendor,they want more quantity let say 250 quantity.

When they amend the PO, System should again trigger release for the respective persons.In Standard SAP, in case of value change, we can set to trigger release.But we have to set the tolerance for that.

They have the following requirements

a) Before GRN, they can amend the PO and System should trigger for PO release

b) After GRN, partial quantity received and they amend the PO and system trigger release in PO.

I got an exit for this.I tested with our ABAPer but it's not working.

Exit_SAPLEBND_002

How to resolve this??

Your suggestions will be highly appreciated.

Thanks & Regards

PKB

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Solved

Former Member
0 Kudos

Hi,

Go to SPRO -- MAterila Mangement - Purchase order - Release strategy and then click on the tab called release indicator - and make the release indicator as 6 and then check

Best regards

Anamika

Former Member
0 Kudos

Hi Pranaya,

Can you try by defining a User Defined field which will marked X in case there are any changes to the PO.

Maintain the User Defined Field as a characteristic with value as X.

The value has to be populated using the exit.

Regards

sindo

Former Member
0 Kudos

Dear All,

Any suggestions or solutions.

Warm Regards