Hi
I have maintained Performance efficiency rate in workcenter with following parameter
calculation for costing - 100, Scheduling --65
When i tested formula for scheduling i got process duration 153.846 Hours for laour hours= 100 Hrs.
When I remove Performance efficiency rate then i got process duration 100 Hours for laour hours= 100 Hrs
Please tell in first case why it is giving 153.846 Hours it should be 65hrs.
Hi,
Its because the calculation is done as duration / performance efficiency.
So in your case you have specified that the efficiency for scheduling is 65% or 0.65. Now when you specify the duration as 100 hours, system calculates it as 100 / 0.65 which is 153.846.
Hope it clarifies.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.