Jan 01, 2010 at 07:21 AM

Unable to create Schedule line(Maintain sch.agreement)

50 Views

Hi experts,

After running MRP i got Planned order for a certain material and for that material procurement type maintained as "Both internal and external" in material master. After completing the process planned order to purchase requisition, i separately created schedule agreement . Now here i am facing one problem that if i create schedule line with reference to purchase requsition i am getting the error Requisition doc. type NB not allowed with doc.type LP.

pls anybody suggest is there any prob made in the above process

Regs,

SR